How to hire an electrical superintendent who can run subs

How to hire an electrical superintendent: when you need one over another foreman, what he owns each day, how to test him and what BLS says he makes.

Updated November 9, 20268 min read5 sources

Photo: Kathleen Austin Kuhn, Pexels

To hire an electrical superintendent, look for a man who has already run foremen or sub crews and dealt with a GC every day, not your best foreman. Test him on a live job, a look-ahead and a punch walk. Construction managers at electrical contractors made a median $55.02 an hour ($114,450 a year), against $44.95 for supervisors (BLS, May 2025).

01Superintendent, general foreman or working foreman?

A working foreman runs a crew and runs pipe, a general foreman runs foremen, and a superintendent runs the whole job: subs, schedule, material and the GC.

Working foremanGeneral foremanSuperintendent
On the toolsMost of the dayNoNo
RunsHis own crewTwo or more foremenForemen, subs and the job
Deals with the GC onToday's workThis week's workThe schedule, look-aheads, punch
Answers toGF or PMPM or ownerOwner or GM

Titles blur from shop to shop. Some call the man running a big multifamily job the GF, some call him the super. What matters is the work: if the job needs one person on site every day who owns everything that isn't wire pulling, you're hiring a superintendent.

02Signs you need one, not another foreman

You need a superintendent when the owner is the only one holding the job together, or when the crews on site aren't all yours.

  • You're the super. You drive job to job all day, and the work slows the days you're in the office bidding.
  • You run subs. You've got sub crews roughing or trimming units, and nobody checks their work before they leave.
  • The GC calls you, not your foreman. Look-aheads, coordination meetings and RFIs land on your phone.
  • Material runs short. Crews stand around because nobody ordered two weeks ahead.
  • Your foremen are maxed. Each one runs as many hands as he can, and the job still needs more. How many men one foreman can run has the ranges and the math on when a foreman should come off the tools.

One owner who opened a branch three years ago told us he can't stay in the field anymore. He wants a lead with 10 to 15 years licensed who runs 5 or 6 hands across 5 or 6 jobs "like it's his own company," and answers only to him. That's a superintendent's job, whatever he ends up calling it.

If you're still working out which slot to fill as you grow, who to hire next as your crew grows puts the superintendent in order with foremen, J-men and apprentices.

03What a superintendent owns day to day

A superintendent owns the job on site: the crews, the subs, the material, the schedule and the punch list.

One contractor who builds mostly apartments told us what his super does:

  1. On site every day. Not checking in, there.
  2. Runs the sub crews. Subs rough or finish 4 to 8 units a day, and he keeps them fed with work.
  3. Checks the punch before subs leave. A unit isn't done until he's walked it. Once a sub crew is gone, getting them back costs days.
  4. Keeps material ahead. He uses templated lists for repeat buildings, so the next building's material is ordered off the last one.
  5. Works off an iPad. Drawings, submittals, a supplier-linked ordering cart, the time clock and the GC's Procore.

The paper and the subs are what's new for a lot of good field hands. As another contractor put it: "Everybody thinks they're a foreman until they're out there doing it."

Write your own version of that list before you post the job. It becomes the ad, the interview and the first 90 days.

04What to ask and what to test

Test the three things that make a superintendent: has he run subs, can he read and build a schedule, and can he handle the GC.

The trap is a strong foreman from a big shop. He ran his own crew well, but the PM did the software and nobody under him was a sub. Ask straight out and get names.

  1. "Tell me about a sub crew you ran." How many men, what scope, what went wrong. Then: "What did you do when they left work unfinished?" A real answer names the scope and the backcharge.
  2. Hand him a 3-week look-ahead. Ask what he'd order this week, which crew starts where, and what he'd raise with the GC. Ten minutes tells you if he reads a schedule or just works off it.
  3. Walk him through a live job. Thirty minutes on a site at the stage your job will be in shows what he notices and what he'd fix first. How to run a job site walk interview has the route and what to listen for. For a super, end it at the GC's trailer and ask what he'd bring up.
  4. Do a punch walk. Put him in a finished unit or a room and give him 15 minutes. Count what he catches.
  5. Ask about the GC. "Tell me about a super who blamed you for a delay. What did you show him?" You want dates, photos and daily reports, not a war story.
  6. Open the software. Have him pull a sheet and a submittal on an iPad, in your system or the GC's. If he hands that to the PM, you're doing it.
  7. Look up his card. On your state board, by license class, same as any hand. Decide who pulls permits before you make the offer.

For the people side (a sloppy J-man, a wrong call from the GC), use the electrical foreman interview questions and score every applicant on the same sheet.

Call two references, ideally a GC super he worked with. Ask one thing: "Would you want him on your next job?"

05What to pay an electrical superintendent

Pay a superintendent above your top foreman, and use BLS construction manager pay as the top yardstick and supervisor pay as the floor.

Electrical contractors, BLS OEWS, May 202525th pct (hourly)Median (hourly)75th pct (hourly)Median (annual)
Construction managers (11-9021)$43.99$55.02$69.61$114,450
First-line supervisors (47-1011)$36.80$44.95$56.84$93,500

Source: BLS OEWS, May 2025, national industry estimates for electrical contractors and other wiring installation contractors. Straight time only: no overtime, per diem, truck or bonus.

Superintendents don't fall in one BLS bucket. O*NET lists "Construction Superintendent" and "Job Superintendent" as sample titles for construction managers, and "Site Superintendent" as a sample title for first-line supervisors. So a super who runs one job in the field often lands between the two medians, and one who runs several jobs and the money lands nearer the manager row.

At the medians, managers make $10.07 an hour more than supervisors, about 22% more ($55.02 minus $44.95, our math). For what union foremen and general foremen make on the wage sheets, see electrical foreman pay by local.

Put the truck, the phone, the iPad and any bonus in writing. A bonus tied to jobs closing on hours, with a number, tells him what you care about.

06Salary or hourly

A non-working superintendent can often be paid a salary with no overtime, but only if the job meets the federal executive test.

The DOL Fact Sheet #17A test: a salary of at least $684 a week, a primary duty of managing, directing the work of "at least two or more other full-time employees or their equivalent," and hiring and firing authority or recommendations that "be given particular weight."

Watch the second part. If he mostly runs sub crews, those men aren't your employees. A super who directs two of your foremen meets that line more cleanly than one who only runs subs. A working foreman who still does the electrical work fails the test no matter what you call him; hiring a working foreman covers that case. State rules can be stricter, so check yours.

07Promote or hire from outside

Promote when a foreman of yours already runs other foremen or subs and wants the job. Hire from outside when nobody in the shop has run a job this size.

Promoting your best foreman has a cost: you lose him on his crew. Try him on one job first, with a set end date and a clear list of what's his. Promoting a journeyman to foreman lays out that kind of trial.

If you hire from outside, the man you want is working. He's a GF stuck under a superintendent at a bigger shop, a super finishing a long job, or someone who ran his own small shop and is done chasing payments. Make the offer within a day of the last interview.

If you need the super or the hands to put under him, see who we already have near you, journeymen to superintendents. No money up front. If you don't hire, you don't pay.

Got more work than guys?

We already found them: 238 qualified electricians, 5+ years each. See who we have near you. No money up front. If you don't hire, you don't pay.

See who we have

FAQFAQs

What's the difference between a superintendent and a project manager?

The superintendent runs the job in the field: crews, subs, material and the daily schedule. The project manager runs it from the office: the contract, billing, change orders and buyout. On smaller shops one person may do both, but the jobs pull in different directions.

How many years of experience should an electrical superintendent have?

There's no set rule. One owner told us he wants 10 to 15 years licensed, and most supers have time as a foreman or general foreman first. Years matter less than what he ran. A man who has run subs and a GC on a job your size beats one with more years who never left his own crew.

Does an electrical superintendent need a license?

It depends on the state and on who pulls the permit. Many shops want a licensed journeyman or master because he's checking licensed work and may sign off for the shop. Check your state board's rules before you write the ad.

Can one superintendent run more than one job?

Yes, if the jobs are close and each has a foreman who can run his crew without him. One owner told us he wants his lead running 5 or 6 small jobs. On one large multifamily or multi-building job, plan on a superintendent on site every day.