Adding a commercial crew to a residential electrical shop
Residential electrical contractor moving to commercial: what changes (license, bonds, prevailing wage, retainage), who to hire first and a starter crew.
A residential electrical contractor moving to commercial needs four things in place before the first bid: a license class that covers the work, bonding capacity, a payroll setup that can handle prevailing wage, and a commercial foreman. Hire the foreman first. The reason to bother is the housing cycle: single-family starts fell 74% from 2005 to 2009, per Census Bureau annual data.
01Why residential shops add commercial work
Commercial work is a hedge against the housing cycle, and the cycle is real.
Single-family housing starts were 1,715,800 in 2005 and 445,100 in 2009, per the Census Bureau's annual housing starts table. That's 74% gone in four years. The swing is smaller now, but it still moves: single-family starts went from 1,012,900 in 2024 to 939,700 in 2025, down about 7%.
One residential contractor doing over 100 houses a month told us why he wants more commercial: "housing stops or slows down." He already had one commercial crew. He'd just won prevailing wage work, including a school, plus a run of gas stations. And he was turning other commercial jobs down because he didn't have the hands to man them.
That's the usual picture. The work is there. The manpower isn't. If you're still deciding what your next hire should be in general, start with who to hire next as your shop grows. This post is for the shop that has already decided to go after commercial.
02What changes when you go commercial
Almost everything outside the wire changes: the license, the paper, the schedule and the way you get paid.
| Area | Residential | Commercial |
|---|---|---|
| Wiring method | Romex, boxes, panels | EMT and rigid, MC, tray, gear |
| Who sets the schedule | You and the builder | The GC, with other trades stacked on you |
| Paperwork | Permit, inspection, invoice | Submittals, RFIs, pay apps, closeout, sometimes certified payroll |
| How you get paid | Draws or on completion | Monthly pay apps, with retainage held back |
| Bonds | Rare | Often required on public work |
License class
Check that your contractor license covers commercial work before you bid it. Some states license residential-only contractors or electricians separately, and a residential-only license doesn't cover commercial work. Your journeymen's cards matter too, not just yours. Rules vary, so confirm with your state's licensing board. If you'll cross state lines for the work, getting licensed to work in other states covers what that takes.
Bonds
Public jobs often require performance and payment bonds, and you need a surety willing to write them. On federal construction contracts over $150,000, the law formerly known as the Miller Act requires both bonds (FAR 28.102-1). States have their own versions for state and local work. Talk to a surety agent before you bid a school, not after you win it. They'll want your financials, and a shop that's only done houses may get a small line to start.
Prevailing wage and certified payroll
Federally funded jobs over $2,000 pay Davis-Bacon rates: at least the locally prevailing wages and fringe benefits for that kind of work (DOL, Davis-Bacon and Related Acts). Certified payroll goes in weekly, for each week covered work is performed, with a signed Statement of Compliance (29 CFR 5.5).
One catch for residential shops that bring helpers along: on these jobs, apprentices can only be paid below the journeyman rate if they're individually registered in a registered apprenticeship program (same rule, 29 CFR 5.5). An unregistered helper gets the full rate for the work he does. Davis-Bacon for electrical contractors goes through wage determinations and fringes line by line. Many states have their own prevailing wage laws for state and local jobs, so check yours.
Retainage and cash flow
Commercial work pays monthly, minus retainage, and the retainage can be your whole margin. On federal jobs, the contracting officer can hold up to 10% of a progress payment if progress isn't satisfactory (FAR 52.232-5). Private GCs write their own retainage into the subcontract, and many states cap it on public jobs, so read both.
Example, not a quote: say you win a $400,000 job and the GC holds 10%. That's $40,000 you don't see until closeout. If your margin on the job is 10%, that's your whole profit sitting in the GC's account until punch is done. Meanwhile you're paying the crew every week. Price that in and have the cash or credit line to carry it.
03Who to hire first: a commercial foreman
Your first commercial hire should be a foreman who has run commercial jobs, not more journeymen.
Your residential hands can pull wire. What they usually haven't done is run a job on a GC's schedule: read a full plan set, chase submittals, coordinate with mechanical, keep material ahead of the crew and walk the inspector through it. That's the foreman's job, and on commercial it's now as much information as it is production.
A long-time commercial contractor told us it plainly: "Everybody thinks they're a foreman until they're out there doing it." His foremen work off an iPad with two or three plan sets, four or five submittals, plus the elevator and mechanical shop drawings, all while running six men.
What to look for:
- Has run commercial jobs as foreman, not just worked on them. Ask which jobs, what size, how many hands, which GC.
- Has handled submittals, RFIs and a three-week lookahead himself, not left them to a PM.
- Can bend, and can show your residential guys how. He's going to be teaching for the first year.
- Has done prevailing wage work if you're bidding public jobs. He'll know what the paperwork asks of him.
On a small start, he'll be a working foreman, on the tools most of the day. Hiring a working foreman who still wears tools covers what to pay him and how to test him.
04How many residential hands can cross over
Some will, some won't, and you find out by testing, not by asking them.
A good residential journeyman can learn commercial. The ones who cross over fastest already bend some pipe, read prints without help and have done light commercial or service work. The ones who struggle have only done new homes and have never been on a job with a GC.
Test each one before you move him:
- Bend. Hand him a bender and a print. Offset, kick, three-point saddle. Watch the time and the waste.
- Prints. Hand him an E sheet and a panel schedule. Ask him to find a circuit and tell you what feeds it.
- Terminations. Make him land a 3-phase panel or a small piece of gear. Ask about torque.
- Job sense. Ask what he'd do if the mechanical guy's duct is where his pipe needs to go.
Move the ones who pass to the commercial crew under the new foreman. Keep the rest on houses. Don't pull your best residential hands off the side that pays the bills to fill a commercial crew they're not ready for. If you're adding journeymen from outside, the eight steps to hire a journeyman apply, with commercial hours as the screen.
One more trap: hiring experienced commercial hands just because they have the years. The same residential contractor told us the journeymen he'd brought on "have bad habits... go from job to job trying to make more money," wanted to run his apprentices, "and at the end of the day I'm paying more to fix their stuff." He hires about 1 in 5 he interviews. Years aren't the test. The work is.
05A starter crew plan
Start with one crew sized to the jobs you can win, and grow it only as your backlog proves out.
| Stage | Crew | Jobs to bid |
|---|---|---|
| Start | 1 commercial foreman, 2 residential J-men who passed the test, 1 apprentice | Small tenant fit-outs, gas stations, small retail |
| After 2 or 3 jobs closed out | Add 1 or 2 J-men with commercial hours | Larger fit-outs, small ground-up |
| Steady backlog | Second crew with its own foreman | Schools and public work if bonding allows |
Check your apprentice count against your state's ratio before you build the crew; journeyman to apprentice ratio rules lists how they work.
Bid what the crew can man. A small crew stretched over a job sized for twice its headcount is how a residential shop gets backcharged on its first GC job. When an award shows up with three weeks' notice, planning manpower against the schedule helps you see who's free and when.
06What to price differently
Commercial bids carry costs residential bids don't, so a residential shop's labor units and markup won't hold.
- Labor units. Conduit runs, gear sets and terminations take hours your house numbers don't show. Track the first jobs closely and fix your units.
- Overhead. Submittals, pay apps, closeout and certified payroll take office hours. Someone has to do them.
- Carry. Retainage and slow pay apps mean you carry payroll for 60 days or more. Count the cost of the money.
- Bond premium. If the job is bonded, the premium goes in the bid.
- Prevailing wage labor. Price the wage determination's rate and fringe, not your shop rate.
If you've got commercial work you're turning down for lack of hands, see the electricians we already have near you. No money up front. If you don't hire, you don't pay.
Got more work than guys?
We already found them: 238 qualified electricians, 5+ years each. See who we have near you. No money up front. If you don't hire, you don't pay.
See who we haveFAQFAQs
Can a residential electrical contractor do commercial work?
Often yes, if your state license covers it. Some states issue residential-only licenses that don't cover commercial work, so check your license class with your state board before you bid. Your crew's licenses have to cover the work too.
Do I need a separate company for a commercial division?
Not usually. Most shops run commercial as a division under the same license and company. Some set up a separate company to keep bonding, insurance or books apart. Ask your accountant and your surety agent.
How much retainage do GCs hold on commercial jobs?
It's set by the contract. Federal jobs allow up to 10% held from a progress payment when progress isn't satisfactory, under FAR 52.232-5. Many states limit retainage on public work. Read the subcontract and your state's prompt pay law before you sign.
Should I hire a commercial foreman or train one of my own guys?
Hire one for the first crew. Your best residential hand can grow into a commercial foreman, but he'll learn faster under someone who's already run the work. Promote from inside on the second crew.
What commercial jobs should a residential shop bid first?
Small, simple, local jobs with short schedules: tenant fit-outs, small retail, gas stations, light commercial service. Skip big ground-up jobs until you've closed out a few and know your labor units.
Sources
- U.S. Census Bureau, New Residential Construction, annual housing starts (xlsx)
- U.S. Department of Labor, Davis-Bacon and Related Acts
- 29 CFR 5.5, Contract provisions and related matters
- FAR 52.232-5, Payments under Fixed-Price Construction Contracts
- FAR 28.102-1, Bonds (formerly the Miller Act), General