Electrical testing technician: the work, NETA and pay

Electrical testing technician work explained: acceptance, maintenance and damage testing, the four NETA ETT levels, how a J-man gets in, and BLS pay data.

Updated November 23, 202610 min read8 sources

Photo: Mikael Blomkvist, Pexels

An electrical testing technician tests gear instead of installing it: new switchgear before it's energized, old gear on a maintenance schedule, and equipment hit by fire, flood or storm. NETA certifies testing techs at four levels, from trainee to senior, with 2, 5 and 10 years of experience behind Levels 2 to 4. BLS has no separate pay code for it; the closest one, substation and relay repairers, had a median of $49.53 an hour (BLS OEWS, May 2025).

If you already bend pipe and land wire for a living, you have half of what a testing firm wants. The rest is test sets, procedures and reports.

01What does an electrical testing technician do all day?

A testing tech proves gear is safe and works, then writes down what he found. Most of the work falls into four buckets.

WorkWhat it isWhen it happens
Acceptance testingTesting new gear before it's turned onEnd of a new build or a big tenant job
Maintenance testingRetesting gear that's been in serviceOn a schedule, often during a planned shutdown
Damage evaluationDeciding what can be saved after fire, flood or stormAfter the event, often for the insurance claim
Switching and outagesTaking gear out of service and back in safelyBefore maintenance, repairs or tie-ins

NETA publishes the specs most of this work follows: ANSI/NETA ATS-2025 for acceptance testing and ANSI/NETA MTS-2023 for maintenance testing (NETA standards). In practice that means insulation resistance, contact resistance, breaker trip testing, protective relay testing, transformer tests and infrared scans, with a report for every piece of gear.

Maintenance testing got a push in 2023. That year NFPA 70B, the maintenance document for electrical equipment, changed from a recommended practice to a standard, which "added the aspect of enforceability" (reported by EC&M). More owners now need a written maintenance program, and someone has to do the testing in it.

The damage work is the part most electricians never see. One testing contractor told us 50 to 80% of everything his company does is testing electrical systems damaged by an event: fire, storm or flood. He said his hands learn things "99.9% of all electricians nationwide will never even understand exists."

02How is it different from wiring work?

Testing is slower, more careful and more paperwork than install work, and it's mostly indoors.

  • You read gear, not prints. Nameplates, one-lines, relay settings and manufacturer test values matter more than conduit routing.
  • You carry test sets, not a bender. The company owns the expensive equipment. You learn to run it and trust it.
  • You write. Every test gets recorded. A sloppy report costs the customer as much as a sloppy termination.
  • Outages run the schedule. Shutdowns land on nights and weekends because that's when the building can go dark.
  • It's indoors. The same contractor told us "99% of everything we do is indoors."

The NEC and NFPA 70E still apply. You'll work around energized gear and do switching, so arc flash training is part of the job from day one. If your safety cards are thin, what OSHA 10, OSHA 30 and NFPA 70E each cover is a good place to start.

For the bigger picture of where testing sits next to service, foreman and estimating moves, see the career paths open to a journeyman.

03What are the four NETA certification levels?

NETA's ETT program has four levels, and each one needs the one below it first (NETA technician certification). The standard behind it is ANSI/NETA ETT-2026. You'll often see the levels written I to IV.

LevelTitleExperienceTraining hours (total)Exam
1TraineeNone setHigh school or GEDBy employer
2Certified Assistant Technician2 years40 safety, 160 electrical100 questions, 2 hours
3Certified Technician5 years64 safety, 400 electricalSame as Level 2
4Certified Senior Technician10 years104 safety, 600 electrical65 questions, 2 hours

Source: NETA, technician certification page, checked Nov 23, 2026.

A few things NETA spells out:

  • Level 1 trainees "are not fully certified technicians." It's the entry point, and you work under supervision.
  • Exams are closed book and proctored. Passing is 410 or higher on a scale of 200 to 500.
  • Two or more years of technical education in an electrical field counts for up to one year of experience.
  • NETA Certified Technicians are employed by a NETA Accredited Company. You get certified through the firm you work for, not on your own.

NETA's page doesn't say whether years spent wiring count toward the experience line. Ask the firm how they'll log your time before you sign.

04How does a journeyman get into testing?

Most hands get in by hiring on with a testing firm as a trainee or assistant and learning on its gear. Your field years make you a faster learner, not a Level 3 on day one.

  1. Find the testing firms near you. NETA lists its accredited companies on netaworld.org. Utilities, big industrial plants and switchgear makers' field service groups test too.
  2. Lead with what transfers. Gear terminations, switchgear and transformer work, LOTO, 70E, reading one-lines, any time on shutdowns or commissioning.
  3. Expect to start under supervision. Plan on Level 1 or Level 2 work while you learn the test sets and the report format.
  4. Ask about the path to Level 2 and 3. Who pays for the training hours, who pays for the exam, and how long it usually takes.
  5. Keep your license current. Testing doesn't always need a state card, but a card keeps your other doors open.

You don't always need a card to get hired. The testing contractor we talked to hires on drive over paper: he told us a third-year apprentice was "running three or four guys" within a week, and "a license doesn't make a good electrician." Other firms will want the card. Ask.

If you're doing data center work now, you've likely watched the commissioning crews test what you installed. What electricians do on data center jobs covers that side, and it's a common way in.

05What do electrical testing technicians make?

BLS doesn't track testing techs on their own. The closest code is 49-2095, powerhouse, substation and relay electrical and electronics repairers, and it had a median of $49.53 an hour, $103,020 a year (BLS OEWS, May 2025).

BLS OEWS, May 2025Median hourlyMean hourly10th to 90th pct hourly
Substation and relay repairers (49-2095), all industries$49.53$48.44$31.60 to $62.46
Same code, testing laboratories$47.93$42.35$22.62 to $53.43
Electricians (47-2111), all industries$30.38$34.37$20.50 to $52.17

Read it with care:

  • It's mostly utility techs. Of the 20,720 people in 49-2095, 13,280 work in utilities, about two in three. Only 210 are counted in testing laboratories. The code is a close cousin of field testing, not the same job.
  • It's straight time. OEWS leaves out overtime, per diem and shift premiums. The electrician line also includes apprentices, which pulls its numbers down.
  • It's market data, not an offer. No firm owes you these numbers.

Union work sometimes pays a premium for it. The IBEW Local 11 inside agreement in Los Angeles County pays a journeyman $67.00 an hour and $70.35 when "performing instrumentation work or NETA testing," a 5% premium, for rates effective Oct 26, 2026 to Jan 31, 2027 (IBEW Local 11 wage sheet). The sheet says that premium goes to 7.5% on Feb 1, 2027. If union sheets are new to you, how to read a union wage sheet walks through one.

Open-shop numbers come from what firms tell you. One field-service manager told us he was planning to hire high voltage techs "capable of switching and substation work" at $50 to $65 an hour, on salary. That's one company's plan, not a going rate.

06What's the travel like?

Most testing work moves around, but it comes in shorter trips than a typical traveler job. How much depends on the firm.

The testing contractor we talked to runs trips of three days to three weeks, averaging 5 to 8 days, with about half the work local. Travel isn't optional there, but "everybody gets their own room," and hands drive company vehicles. His reason: "if the guys are comfortable and they rest good, they work good."

The field-service manager runs the other way: techs out at least four weeks at a time, then home, still paid on salary. He told us about his own last year in the field: 309 days on the road and 119,000 miles.

Same trade, two very different lives. Ask which one you're signing up for. If the job pays per diem, what per diem should look like helps you check the number, and the traveling electrician guide covers the rest of life on the road.

07Questions to ask a testing firm before you move

Ask about the path, the gear and the road. A firm that answers these straight is worth a second look.

  1. Are you NETA accredited? If not, how do I get certified working here?
  2. What level do I start at, and what's the plan to Level 2 and Level 3?
  3. Who pays for training hours and exams, and do I owe it back if I leave?
  4. What's the split between acceptance, maintenance and damage work?
  5. How long are trips, how often, and is the room my own?
  6. Company truck or my own? Who pays for drive time?
  7. Hourly or salary? If salary, what happens to overtime and home weeks?
  8. How much is nights and weekends for outages?
  9. Who reviews my reports while I'm learning?

Then put the answers next to your current job. Comparing two job offers line by line shows how to count the truck, the per diem and the overtime, not just the rate.

Before you talk numbers with a testing firm, get your local pay report to see what electricians with your license make near you. Takes about a minute and your boss never hears about it.

See what your license pays near you.

Tap a few answers and see what electricians with your license make in your area. Free, about a minute, and your boss never hears about it.

Get my local pay report

FAQFAQs

Do you need to be a licensed electrician to be a testing technician?

Not always. NETA's levels are built on experience and training hours, not a state license, and some testing firms hire apprentices with drive. Others want a journeyman card, and some work may need one where you are. Ask the firm.

How long does it take to get NETA Level 3?

NETA sets 5 years of experience plus 64 hours of safety and 400 hours of electrical training for Level 3, and you have to hold Levels 1 and 2 first. Up to one year can come from two or more years of technical school. Field years only count if the firm can log them toward NETA's experience line.

Can I take the NETA exam on my own?

No. NETA Certified Technicians are employed by a NETA Accredited Company, so you get certified through the firm you work for. Ask in the interview who sets up and pays for your exam.

Is electrical testing a good move for an older electrician?

It can be. The work is mostly indoors and lighter on your body than pulling wire, but outages mean nights and weekends, and most firms travel. Count the road before you count the easier days.

Is testing the same as commissioning?

They overlap. Acceptance testing is often one piece of commissioning on a new build, while commissioning also checks that whole systems work together. A testing tech can work on both.